Torrent Power is setting up a 300 MW solar power plant in Gujarat investing Rs.1,250 crore. It will be commissioned in 18 months of the PPA signing. Tariff has been set at Rs.2.22/KWH for 25 years. Torrent has already executed 648.5 MW wind project and 138 MW solar projects. Currently, there are 515 MW renewable projects under execution.
Torrent Power is setting up a 300 MW solar power plant in Gujarat investing Rs.1,250 crore. It will be commissioned in 18 months of the PPA signing. Tariff has been set at Rs.2.22/KWH for 25 years. Torrent has already executed 648.5 MW wind project and 138 MW solar projects. Currently, there are 515 MW renewable projects under execution.